Felixstowe Docks
July 27, 2016 / Corporate

Felixstowe Docks

The Port of Felixstowe is not just Britain’s biggest and busiest port, it also boasts the best connections. Shipping lines operating from the port – which is the main hub of the ‘Haven area’ that includes Harwich and Ipswich – serve 365 ports around the world. And on terra firma, Felixstowe is just as well situated to distribute goods throughout the country. Some 70% of the containers coming through the port are delivered to the ‘Golden Triangle’ – an area in the middle of Britain where the high street brands and online retailers have their national distribution centres – only a short haul away.

 

 

Though the port has developed good rail links, the bulk of the 3 million-plus

container units it handles travel through the port gates by road. The toll from the many thousands of trucks beating a path along the access road to this import and export hub is also, inevitably, heavy.

Over the years the Port Authority’s engineers have specified a range of materials to combat the problem of deformation. The materials used have ranged from traditional hot rolled asphalt (HRA) to advanced thin surfacing materials, but until now, those efforts have met with limited success.

The biggest issue has been the rutting of the pavement. Trucks passing through the gates of the port use a two-way, two-lane access road. Unlike on a motorway where there is a mix of vehicles and choice of lanes, the unrelenting, ‘channelized’ flow to and from the port is of heavy goods vehicles that barely deviate from the same track. Ploughing the same furrows, their wheels accelerate wear on the road

surface, leading to ruts, cracking and further damage as the weather elements go to work beneath the rapidly deteriorating surface.

The civil engineering team at Felixstowe and its contractors R W Hill (Felixstowe) Ltd and Waveney Surfacing had already decided to use a thin surfacing with a polymer- modified bitumen when they approached asphalt supplier Eurovia Roadstone.

 

“Several solutions were considered but the nature of the site and the type of traffic involved meant that UL-M would be the most resilient for this application,” says David Jones, Technical and Systems Manager, Eurovia Roadstone.

 

UL-M has a proven international track record (see box) but Jones could also point to a similar application closer to home. Lanes one and two of the Queen Elizabeth II Bridge were resurfaced with UL-M, more than five years ago, when the Thames crossing was operated by the Eurovia Group’s joint venture, Le Crossing.

 

This surfacing is still bearing up well under the daily onslaught (more than 140,000 vehicles use the M25’s Dartford-Thurrock Crossing each day), and it’s believed to be the longest life cycle yet for the toll booth sections.

 

Resurfacing of the port’s access road was postponed twice due to adverse weather before going ahead on Saturday 20 April 2013. Waveney’s team planed off the old, failing surface to a depth of 40-50mm for the UL-M course. During production of the 116 tonnes of material, samples were tested at Eurovia’s Ipswich laboratory to ensure it conformed to the design mix.

 

On site in Felixstowe, Eurovia Roadstone’s technician carried out an audit of the laying process, ensuring the material was installed to the system’s specific guidelines, an integral part of which is the use of a bond coat. This provides an excellent bond to the underlying substrate whilst also providing waterproofing, ensuring a greater service life of the whole pavement.

 

“The whole operation went exceptionally well,” says John Murphy, Contracts Manager of Waveney Surfacing. “The material supplied and the cooperation from the plant were first-class, and the attention of Eurovia Roadstone’s materials technician also played such an important part in the successful completion of the contract.”

 

R W Hill (Felixstowe) Ltd and Waveney Surfacing have been associated with maintenance of Port of Felixstowe infrastructure for over 30 years and have been supplied by Eurovia for over 24 years, a long lasting relationship.

 

The toll of traffic on the access road can only get heavier. With Felixstowe aiming to double capacity by 2030, the port’s infrastructure – like its link to the British road network – must bear the burden of this growing trade.

 

 

    Latest news

    Considerate Constructors win for Ringway at Bletchley
    November 6, 2017 / Corporate

    Considerate Constructors win for Ringway at Bletchley

    Ringway Infrastructure Services has won the silver award at this year’s Considerate Constructors Scheme company awards.
      Corporate Responsibility Report 2016
      November 2, 2017 / Corporate

      Corporate Responsibility Report 2016

      Eurovia UK commits to the next generation by joining The 5% Club
      October 26, 2017 / Corporate

      Eurovia UK commits to the next generation by joining The 5% Club

      Eurovia UK, leading highways infrastructure and maintenance company has showcased its commitment to the next generation by joining The 5% Club, an industry led initiative focussed on driving momentum into the recruitment of apprentices, graduates and sponsored students.